Lower Lupton Bottom

Zak has been asked to rehabilitate the existing diversion structure across the Platte River. The project includes rip rap, grouted boulders, concrete apron, and sheet piling.

Location: Fort Lupton, CO
Owner: Lower Lupton Bottom Ditch Company
Contract Amount: $500,000.00
Start Date: 1/14/2018
Completion Date: 4/14/2018


see below to scroll through photos & enlarge
 

Project Updates:

The river diversion is complete and phase 1 sheet piling is installed. Structural concrete footings are placed. We will begin working on the concrete apron and grouted boulders.

Updated By: admin

As always, weather or encountering unknown conditions may cause unforeseen delays to the construction schedule. Every effort will be made to inform you and keep you apprised of changes.